Funding
$145M DOE grant + $50M Michigan funding.
Project Advancement Plan
Initiate Midland and Champion permit applications
Identify and finalize Midland and Champion sites
Commence Midland FEL-3 engineering
Advancing Site Development
Complete site acquisition for Midland and Champion facilities
Order long lead equipment for Midland
Obtain permits for Midland
Develop Midland site build-out package and complete site construction
Complete Champion process design package development
Launch of ReCover™ facility
Complete Midland equipment installation, testing, and commissioning
Midland first product
Complete Champion FEL-3 engineering
Order long lead equipment for Champion
Complete Champion site design
Launch of ReClaim™ Facility
Midland commercial operation
Complete Champion site construction
Complete Champion site commissioning prep
Expansion to Multi-Plant Ecosystem
Complete Champion equipment installation, testing and Commissioning
Champion first product and commercial operation